Distribution Dispatching Center Project 2nd Stage plans to construct 7 distribution system dispatching centers in order to
control dispatching system and Commumication system network by optical fiber in the north, north east and south. The 7
Centres will be located at Chiangmai, Phitsanulok, Nakhon Si Thammarat, Yala, Udon Thani, Ubon Ratchathani and Nakhon
Ratchasima. Power System control and dispatching and solution to outages can be handled rapidly and safely. The total
investment cost is 8,427 Million Baht for 6 years.

Client: Provincial Electricity Authority / KEMA

Location: Regions in Thailand (N1,N2,S2,S3,NE1,NE2 & NE3)

Completed date: March 2008